We're planning a bathroom renovation and I just wanted to check I have the right order of tasks:
1. Isolate plumbing and electrical
2. Remove existing shower, vanity, fittings and tiles
3. Demolish floor and water damaged subfloor
4. Install subfloor
5. Install tile underlay
6. Waterproof floor and walls where tiles will go.
7. Tile floor and walls
8. Install shower, vanity and fittings
9. Silicon seal around shower and vanity
10. Install lights and extractor fan and get plumbing electrical back on
9. Paint