Hi there,
I am just chasing some advice for the ideal sequence for jobs in our bathroom reno.
I completed all the demo, the plumber has been in to sort out floor wastes and chase + install all the pipes in the walls for the double vanity and double shower. Brickie was around yesterday to construct the hob and nib walls.
Struggling to work out the next steps from here. I was thinking I would put the vanity in before tiling as it is quite a large vanity and will save us some money for tiling labour. If I did this, I think I will need an extra cabinet panel either side of the vanity to allow for the thickness of the tiles + adhesive so the vanity doors can still open?
But will I need to have the brick nib walls (and any other walls that need it) rendered before the vanity can go in? Or can this be done after the vanity? Obviously this would change the dimensions of my vanity slightly so would need to know before ordering the cabinet.