Good morning,
I am sheeting a timber framed ledge in our shower with villaboard before it is waterproofed and tiled and was just wondering what is the best way to run the sheeting on top of the frame in this corner to minimise issues with movement down the track.
Should I run the right hand piece all the way into the corner and then butt the left hand piece against it so no villaboard is crossing the corner intersection?
Or should I run the left hand piece all the way into the corner across the intersection, and then butt the right hand piece into it?
I’m thinking the first option is better as the two frames being fixed to two different walls may move at different rates. So if a piece is bridging the intersection it could buckle or warp and start causing waterproofing issues or grout/tile cracking. With no pieces crossing the intersection the tiler can run silicon at the corner joins to hopefully minimise movement issues.
What are your thoughts?