The project:
We bought out little place in Rosebud to renovate. We decided it was time for the backyard to be renovated the backyard and add a pool.
- Materials:
All our items were sourced from Bunnings. Treated pine sleepers, plants, hardiplank, lights, treated pine for structures, paint and all fixings.
- Tools:
Again AEG tools all purchased from Bunnings including hammers, levels, brushes, warner spray guns and more.
- Step 1:
retaining wall first as specified by the engineers using 3m x 200x75 sleepers and galvanisedH posts with ready mix.
- Step 2:
once pool and concrete bondbeam was is we used 140x90 pine to build frame for the cladding.
- Step 3:
fixed off the hardiplank then painted using our Wagner spray gun. Taubmans all weatherpaint.
- Step 4:
Glass panels also purchased from Bunnings for the safety barrier.