Hello,
Have purchased a cubby house and would like to raise it off the ground to a height of about 1m as I would like to incorporate a sandpit beneath. Have a few ideas in mind but not exactly sure which approach would be most ideal and wanting some advice/recommendations. The cubby house is 2.7m x 2.5m. My intention is to have 9 posts dug at a dept of 600mm and at a width of 180mm using 90mm x 90mm H4 treated pine posts. To build the subfloor I was going to have two bearers and about 5-6 joists. Am not exactly sure which way the bearers should run and how they should attach to the posts.
Also how should the joists be attached to the bearers, just nailed in on an angle, bugle screws or joist hangers?
And what would the recommended size of the bearers and joists be?
Tagging @MitchellMc for ideas.
Picture below is the idea that I have.

Thanks in advance