Steps
Step 1
Demolish old kitchen cabinets.

Step 2
Remove old wall coverings (tiling, Gyprock) and insulation. Run new power lines and plumbing.

Step 3
Install new insulation and Gyprock. Joint, sand, repeat.

Step 4
Prime Gyprock, install new door and window trim, and custom cornice for LED lighting.

Step 5
Paint areas of walls that will be exposed (no tile or cabinets) and install upper cabinets.

Step 6
Install lower cabinets, benchtops and finish painting trim ready for tiling.

Step 7
Tile backsplash.

Step 8
Install appliances and cupboard doors.

Step 9
Custom wall LED lights, under cabinet lights, handles, tap, silicone, roller blinds, filler covers between cabinets.

Step 10
Upper and lower trim on wall cabinets. Skirting boards, feature wall, custom utensil cabinet.