My kaboodle kitchen project took me 9 weeks from demolition to cutting trenches in my slab to the final cupboard door installed.
The pantry and cupboard above the oven and fridge are custom made from melamine board as the kaboodle cabinets were not available in the size we needed. All in all it was a great project that I learnt a lot from along the way.
Materials
kaboodle cabinets, melamine board, MDF board, mondella sink, laminate benchtop
Tools
too many too remember
Steps
Step 1
1. Demolition
2. Trench the slab to move plumbing
3. Run wiring and plumbing
4. Plaster
5. Assemble cabinets
6. Install cabinets
7. Install bench tops
8. Install appliances
9. Make and paint all doors and draw fronts
10. Install doors and draw fronts